Our projects

Development of "green" energy at NLMK Lipetsk

TRT operation mode: continuous, 24/7, 8600 hours/year

Project target:

In-house electric energy generation using potential BF-6 and BF-7 gas pressure energy.

From TRT plant, the blast furnace gas is supplied as fuel to the Recovery Co-generation Plant, which altogether significantly improves the efficiency of secondary energy resources utilization.